Flood Zone & Floor Height Checker

Pick your FEMA zone and project, enter the flood elevations from your map and the ground height at the house, and see how high the lowest floor has to be and how far that is above grade. The 3D lot shows the 100-year and 500-year water, the required floor line and the fill pad or piers.

Building your lot in 3D…

Drag to turn · scroll or pinch to zoom · blue is the 100-year water, light blue the 500-year, green the required floor · heights are above your existing grade

1. Your lot and project

2. Elevations from your maps

ft
ft
ft
ft

Use the same datum for every number (usually NAVD88). Leave a box empty if you do not know it. The street crown only matters for unincorporated Harris County.

Find the numbers: FEMA Map Service Center for your zone and BFE, the Harris County Flood Education Mapping Tool (FEMT) for the floodplains around your lot, and the City of Houston Floodplain Management Office (832-394-8854, [email protected]) or Harris County Engineering (713-274-3900) for the 500-year elevation.

3. The house

sq ft
in
ft

Above the raise limit, the tool shows pier-and-beam as the likely foundation. That limit is a rule of thumb, not a code number.

Edit prices typical ranges — replace with your quotes
$/cu yd
$/cu yd
$/cu yd
$/sq ft
$/sq ft
$/sq ft
$/sq ft
$/sq ft
$/sq ft

Published ranges: HomeGuide lists clean fill dirt at about $8 to $25 per cubic yard delivered, and roundups put stem walls at about $5 to $16 per sq ft and pier-and-beam foundations at about $9 to $12 per sq ft. We widened the fill range to cover spreading and compacting. Taller piers cost more than these averages.

Required lowest floor elevation

—

Which rule applied

Rough cost to raise the floor fill, stem wall or piers
OptionLowTypicalHigh

The highlighted row is the option the tool shows in 3D. Engineering, compensating storage, the elevation certificate and permits are not included.

Notes and things to check
    How the required elevation is worked out

    City of Houston (Chapter 19, effective September 1, 2018): the City's guideline summary sets the lowest floor for new residential construction in both the 100-year and 500-year floodplains at the 500-year elevation plus 2 ft. A residential addition over 1/3 of the footprint also gets 500-year plus 2 ft in both floodplains. A residential addition of 1/3 of the footprint or less is 100-year plus 1 ft in the 100-year floodplain and has no requirement in the 500-year floodplain. Substantial improvement is 500-year plus 2 ft in the 100-year floodplain and has no requirement in the 500-year floodplain. Fill placed below the 500-year elevation must be offset with compensating storage.

    Unincorporated Harris County: the County's floodplain regulations (amended effective January 1, 2018) require, for a Class II permit (land in an A zone or below the 100-year elevation), that the top of the subfloor of the lowest habitable floor be 24 in or more above the 500-year elevation, or 12 in above the crown of the nearest public street, whichever is higher. In a floodway or V zone the bottom of the lowest supporting member must be 36 in above the 500-year elevation. We applied this to new construction and substantial improvement. The text we could read does not give a clear number for additions or for lots only in the 500-year floodplain, so the tool tells you to check with Harris County Engineering.

    Everywhere else: the federal minimum for the National Flood Insurance Program is that new residential construction and substantial improvements in A, AE and AH zones have the lowest floor at or above the base flood elevation. Many communities require extra height (freeboard), so ask your local floodplain administrator.

    What the 3D lot shows

    Everything is measured up from your existing grade. The darker blue plane is the 100-year water level (BFE), the lighter one the 500-year level, and the green plane is the required floor. The house sits on a slab at your normal slab height when no raise is needed, on a fill pad with 3-to-1 side slopes when the raise is small, and on piers and beams when it is larger or when Harris County's Class II rules apply. The stairs, ruler and labels show the heights.

    The model is an illustration. Real pads, piers and grading need an engineer's design.

    Before you build
    • Ask the floodplain office for the 100-year and 500-year elevations for your parcel in writing.
    • Hire a surveyor for an elevation certificate. A post-construction certificate is typically required.
    • Ask about compensating storage if you plan to add fill.
    • Flood insurance rates depend on how far the lowest floor sits above the BFE. Ask your agent.
    • See our Houston Permit Checker for the permits that go with floodplain work.

    This tool is a planning aid, not a floodplain determination or an elevation certificate. Rules change, so confirm every number with the floodplain office before you design or pour.

    Sources

    The Harris County reading comes from a draft of the amendment, not the adopted text, so it is the part to confirm first. The fill price range and the raise limit for fill are our assumptions.

    Estimates only — not engineering, legal or code advice. Check requirements with your local building department and a licensed professional before you build.

    Common questions

    How high does a new house have to be in a Houston floodplain?

    Under the City of Houston's Chapter 19 (effective September 1, 2018), a new home in the 100-year or 500-year floodplain must have its lowest floor at least 2 ft above the 500-year flood elevation. With this tool's defaults (500-year elevation 56.5 ft, existing grade 52.0 ft) that is 58.5 ft, which is 6.5 ft above grade and 6.0 ft above a normal slab that sits 6 in above grade.

    Do additions and remodels have to be raised too?

    In the City of Houston, a residential addition over 1/3 of the footprint, and any substantial improvement in the 100-year floodplain, must also be 2 ft above the 500-year elevation. A residential addition of 1/3 of the footprint or less in the 100-year floodplain must be 1 ft above the 100-year elevation, and has no requirement in the 500-year floodplain. A substantial improvement in the 500-year floodplain only has no elevation requirement. A substantial improvement costs 50% or more of the structure's market value.

    What are the rules in unincorporated Harris County?

    The Harris County floodplain regulations, amended with an effective date of January 1, 2018, require the top of the subfloor of the lowest habitable floor in the 100-year floodplain to be 24 in or more above the 500-year elevation, or 12 in above the crown of the nearest public street, whichever is higher. This tool applies that for new construction and substantial improvement. For additions and for lots only in the 500-year floodplain it says to check with Harris County Engineering, because the rule text we reviewed does not give a clear number.

    Where do I find my base flood elevation?

    Look up your address on the FEMA Flood Map Service Center to get your zone and, for AE zones, the base flood elevation (BFE). The Harris County Flood Education Mapping Tool (FEMT) shows the floodplains around your lot. The 500-year elevation is the less public number, so ask the City of Houston Floodplain Management Office or Harris County Engineering, or look at an elevation certificate for your lot.

    Does raising the slab mean adding fill?

    Sometimes. Up to a few feet, a fill pad or a stem wall under the slab is common. Higher than that, a pier-and-beam foundation is usually cheaper and lets floodwater flow under the house. In the City of Houston, fill placed below the 500-year elevation has to be offset with compensating storage. Harris County press coverage of its 2018 rules says new buildings in the 100-year floodplain need pier-and-beam foundations. Confirm with the floodplain office.

    What does it cost to raise the floor?

    Published ranges for foundation work are roughly $5 to $16 per sq ft for a stem wall and $9 to $12 per sq ft for pier-and-beam, and clean fill dirt runs about $5 to $30 per cubic yard delivered. For the default 2,000 sq ft house raised 6 ft, this tool shows about $21,000 for pier-and-beam (typical), with fill and stem wall shown as alternatives. Engineering, compensating storage and permits are extra.